Welcome to scot-rail.co.uk, Scotland's online railway community. The group is for any rail enthusiast interested in the railways and trains of Scotland. It not only consists of the wiki that you're reading now, but a busy online forum and mailing list, which is accessible to anyone who registers. If you would like to join in, all you have to do is register with us for free.
Breadcrumb navigation
Planned Engineering Work during 2008.
A register of disruptive possessions is listed in Network Rail's Rules of the Route (Section 7) document.
ROTR 70sc08.pdf (471.11 Kb)
Below is a listing of daytime line blockages, and service alterations, for the period December 2007 - March 2008.
Saturday 8th - Sunday 9th December 2007
no major work
Sunday 16th December 2007
Main Worksites:
- Millerhill Yard: Track Renewal (Through Siding F7)
- Niddrie end of Milllerhill blocked. Any freight trains via Monktonhall Jn (with reverse at Drem if necessary).
Sunday 23rd - Monday 24th December 2007
Cross-Border Service Alterations:
- GNER trains start/terminate at Peterborough
Tuesday 25th December 2007 Christmas Day
Main Worksites:
- WCML 'Clyde Viaduct' (near Abington): Track renewal, Down line, 55m800y - 56m700y. (Mon 2230 to Thu 0640)
- No passenger trains running
Wednesday 26th December 2007 Boxing day
Main Worksites:
- Glasgow Central: Resignalling work (Tue 0035 to Thu 0500)
- Passenger service in SPT area only; 'Saturday service'.
- Glasgow Central (GLC) closed,
- Bus only: GLC - Whifflet, GLC - Paisley Canal, Shotts - Motherwell
- Bus: GLC - Crossmyloof (for East Kilbride/Kilmarnock trains)
- Bus: GLC - Pollokshields West (for Newton train)
- Bus: GLC - Pollokshields East (for Neilston trains)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- FSR Christmas Service alterations
Main Worksites:
- Shields Junction: S&C renewals (Tue 0030 to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- FSR Christmas Service alterations
Main Worksites:
- Edinburgh Waverley: OHLE works at West end (Mon 2330 to Sat 5th Jan 0430))
- Bay platforms 12,13,18 available from Thursday.
- Bay platforms 14,15,16,17, and lines X&Y through Mound tunnels blocked until 1st Jan.
- Edinburgh - Glasgow Queen Street: 1/2 hourly service.
- Haymarket/North Berwick trains start/terminate at Edinburgh Waverley.
- Fife Circle and Cowdenbeath trains start/terminate at Haymarket.
- NXEC and CrossCountry trains to/from Aberdeen/Inverness diverted via South Suburban line (do not call Haymarket).
- FSR Christmas Service alterations
Cross-Border Service Alterations:
- Virgin Trains: No trains to London Euston, start/terminate at Coventry
- Caledonian Sleepers: Diverted via ECML, reverse at Wembley for Euston.
Saturday 29th - Sunday 30th December 2007
Cross-Border Service Alterations:
- NXEC: Trains start/terminate at Newcastle (bus to Darlington)
Saturday 29th - Monday 31st December 2007
Cross-Border Service Alterations:
- Virgin Trains: No trains to London Euston, start/terminate at Coventry
- Caledonian Sleepers: Diverted via ECML, reverse at Wembley for Euston.
Saturday 29th - Monday 31st December 2007
Wednesday 2nd - Friday 4th January 2008
Main Worksites:
- Shields Junction: S&C renewals (Tue 25 Dec 0030 to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Clyde Coast trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- No Passenger service on 1st January
Main Worksites:
- Edinburgh Waverley: OHLE works at West end (Until Sat 5th Jan 0430)
- Bay platforms 14,15,16,17, and lines X&Y through Mound tunnels blocked
- Edinburgh - Glasgow Queen Street: 1/2 hourly service.
- Haymarket/North Berwick trains start/terminate at Edinburgh Waverley.
- Fife Circle and Cowdenbeath trains start/terminate at Haymarket.
- NXEC and CrossCountry trains to/from Aberdeen/Inverness diverted via South Suburban line (do not call Haymarket).
- 1st January: No First ScotRail trains, NXEC runnning South of Edinburgh only.
- FSR Christmas Service alterations
Wednesday 2nd January 2008
Main Worksites:
- Glasgow Central: Resignalling work (Tue 0035 to Thu 0500)
- Glasgow Central (GLC) closed,
- Bus only: GLC - Whifflet, GLC - Paisley Canal
- Bus: GLC - Crossmyloof (for East Kilbride/Kilmarnock trains)
- Bus: GLC - Pollokshields West (for Newton train)
- Bus: GLC - Pollokshields East (for Neilston trains)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr)
- FSR altered services Edinburgh - Shotts - Motherwell
- Virgin Trains and FTPE: start/terminate at Motherwell
- NXEC: Glasgow Central trains start/terminate at Edinburgh
- FSR Christmas Service alterations
Wednesday 2nd January 2008
Main Worksites:
- Larbert - Plean: Resignalling work
- Glasgow / Edinburgh - Aberdeen at 'Sunday service level'
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- 2-hourly Stirling - Perth - Dundee shuttle
- Hourly Glasgow - Falkirk Grahamston - Edinburgh serices
- Inverness trains via Fife
- FSR Christmas Service alterations
Saturday 5th - Sunday 6th January 2008
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Main Worksites:
- Shields Junction: S&C renewals (until to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- FSR Christmas Service alterations
Main Worksites:
- Cauldcotts (between Arbroath & Inverkeilot): Track Renewal (Down line, 21m 177y to 21m 1635y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Sunday 6th January
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 12th - Sunday 13th January
Main Worksites:
- Kinnaber : Track Renewal (Up line, 203mi 952y to 205mi 302y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 13th January
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Shields Junction and GARL works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 19th - Sunday 20th January
Main Worksites:
- Kinnaber : Track Renewal (Up line, 203mi 952y to 205mi 302y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 20th January
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Shields Junction and GARL works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 26th - Sunday 27th January
Main Worksites:
- Glenury (north of Stonehaven): Track renewal (Down line 225mi 691y - 225mi 1053y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 27th January - Friday 1st February
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 2nd - Sunday 3rd February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 06:00 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Slateford Junction: Switch and Crossing renewal Cancelled?
- No trains Edinburgh - Carstairs / Livingston South
- Sleepers diverted
Saturday 9th - Sunday 10th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 06:00 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Sunday 10th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Saturday 16th - Sunday 17th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:35 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Sunday 17th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal
- Ladybank: Signalling work
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Saturday 23th - Sunday 24th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:35 Saturday to 05:30 Monday
- Dalmakether: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Sunday 24th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Main Worksites:
- Shields Junction (S&C Tamping) and OHLE works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 1st - Sunday 2nd March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Dalmkether: Track renewal, Up Line (33m0y - 33m1748y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 2nd March
Main Worksites:
- Gorton: Track renewal (58m1627y - 59m609y)
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal follow-up work
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Main Worksites:
- Shields Junction (S&C Tamping) and OHLE works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 8th - Sunday 9th March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Wamphhray: Track renewal, Dn Line (34m838y - 35m830y)
- Abington South: Track renewal, Dn Line (53m1193y - 54m1540y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 9th March
Main Worksites:
- Soldiers Trench (South of Rannoch): Track renewal (60m1409y - 61m839y)
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Saturday 15th - Sunday 16th March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Auchencastle: Track renewal, Up Line (41m90y - 41m1563y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 16th March
Main Worksites:
- Gorton: Track renewal
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Larbert - Stirling: Signalling work
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- Glasgow - Stirling diverted to Falkirk Grahamston
- Edinburgh - Falkirk Grahmston, Bus to/from Dunblane
- Glasgow - Inverness trains via Fife.
- NXEC Highland Chieftain via Fife.
Saturday 22nd - Sunday 23rd March Easter Day
Main Worksites:
- Zone boundary to Carstairs South Jn: Blocked 21:10 Saturday to 11:40 Sunday
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
- First Transpennine Express: No trains operating north of Carlisle
Saturday 22nd - Monday 24th March
Main Worksites:
- Stirling - Alloa - Kincardine: Signal commissioning
- Larbert: Track renewal, Down Line (109m1612y - 110m498y)
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- Glasgow - Stirling / Dunblane diverted to Falkirk Grahamston and through to Edinburgh (Sat/Mon)
- Glasgow - Stirling diverted to Falkirk Grahamston (Sunday)
- Newcraighall/Edinburgh - Falkirk Grahmston, Bus to/from Dunblane
- Glasgow - Inverness trains via Fife.
- NXEC Highland Chieftain via Fife.
Cross-Border Service Alterations:
- No Virgin Trains services to London Euston - all terminate Birmingham/Coventry
- Caledonian Sleepers run ECML on Sunday and Monday nights
Sunday 23rd March Easter Day
Main Worksites:
- Glengarnock: Re-railing (19m880y - 21m10y)
- Glasgow Central - Johnstone, bus to Irvine (am) / Killwinning (pm)
- Ayr - Largs (via Byrehill Jn - Dubbs Jn) until 12.43
- Kilwinning - Ayr / Largs (pm)
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
Cross-Border Service Alterations:
- Busses replace trains Carlisle - Preston on Easter Sunday.
Saturday 29th - Sunday 30th March
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Saturday 29th - Friday 4th April
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April
Saturday 29th
Main Worksites:
- Ampherlaw: Track Renewal (Down line, 77m2y - 92m452y)
- Kaimes: Track Renewal (Down line, 92m1000y - 92m1479y)
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 30th March
Main Worksites:
- Lochwinnoch: Track renewal, Up line (17m550y - 16m1095y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 5th - Sunday 6th April
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Saturday 5th - Friday 11th April
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April
Saturday 5th
Main Worksites:
- Ampherlaw: Track Renewal (Down line, 77m452y - 77m900y)
- Kaimes: Track Renewal (Down line, 92m1479y - 92m1759y)
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 6th April
Main Worksites:
- Lochwinnoch: Track renewal, Up line (17m550y - 15m1638y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Carmuirs West: S&C tamping
- Glasgow - Stirling/Aberdeen trains reverse Polmont until 12.30pm
Main Worksites:
- Stirling: Track renewal, through platforms 6 and 9
- None.
Saturday 12th - Sunday 13th April
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April.
Saturday 5th
Main Worksites:
- Kirknewton/Kaimes: Drainage work. Curriehill: OLHE work
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 6th April
Main Worksites:
- Lochwinnoch/Beith: Track renewal, Up line (17m550y - 15m1638y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Stirling: Track renewal, through platforms 6 and 9
- None.
External Links:
- First ScotRail: Journey Check
- NXEC: Amended timetables
- Virgin Trains: Engineering Works
- CrossCountry: Travel Updates
- FTPE: Engineering Works
- National Rail: Planned Engineering Works
- Network Rail: Operational Rules (ROTP)
- ROTP: register of possessions 2008 (2mb PDF)
- ROTP: register of possessions 2009 (2mb PDF)